All companies engaged in welded production are required to establish and implement ISO 3834 Welded Manufacturing Competence Management System in their enterprises and then obtain ISO 3834 Certificate. After the system is applied for a while, the certification process is initiated by applying to a certification body.
In general, the first step is taken by completing an application form to be obtained from certification bodies. However, it is necessary to be careful in the selection of the certification body and to investigate whether it is authorized by a national or international accreditation body.
After the evaluation of the application form, the certification body prepares a contract. The scope of the service to be provided in the contract should be clear and understandable. As soon as the contract is signed by the applicant company, the work starts and the certification body appoints a sufficient number of auditors depending on the size of the enterprise and the number of employees.
Audits are performed for all industrial companies that make production using welding based on ISO 3834 standard. Audits are carried out on the basis of TS EN 15085 standard for enterprises engaged in the production and repair of railway vehicles and parts. The auditors first perform a preliminary audit of the documentation work. If there are any nonconformities or errors during the pre-audit, they are requested to be remedied. Field inspections are not carried out until the documentation deficiencies are eliminated.
- TS EN ISO 3834 Certification Process
For applicants, the process includes the following stages:
- a) Certification Application is made with “F - 138 Process-Product Certification Application Form..
Process-Product Certification Manager / Directive Manager reviews the application and
the applicant's process to the standards and certification covered in the application form
according to the certification criteria determined in the program. Applicants eligible
If it is found, the related organization is submitted with ”F - 063 Bid Form teklif.
- b) After confirmation of the Quotation by the customer, by the Certification Engineer, “F -
140 Process-Product Certification Agreement ”is prepared and the agreement is signed mutually.
- c) Process-Product Certification Manager / Directive Manager, chief
appoint the auditor and auditor.
- d) - F - 162 TS EN ISO 3834 Checklist tarafından by the Certification Engineer
items are requested to be filled and sent.
- e) Certification Engineer na F - 161 Process-Product Certification Audit Plan Form ”
F - 172 Page 4 / 8
Audit Plan prepared in accordance with the planned audit date at the latest one week
first to the company. Verbal or written confirmation is obtained from the customer.
- f) At least one person from the management of the company and the process to be certified
at the opening meeting with the participation of the authorities, in the explanations about the audit plan
information about the evaluation. In the meeting, “F - 174
Opening-Closing Meeting Minutes are recorded in the relevant section.
- g) The applicant's process and quality system shall be in accordance with TS EN ISO 3834-2 (or TS EN ISO 3834-3).
or TS EN ISO 3834-4).
- h) Review of the issues mentioned in the Evaluation, Checklist; Related procedure, instruction
or control of forms and field inspection. Evaluation findings, “F - 162 TS
EN ISO 3834 Checklist ır.
ı) The lead auditor and the auditor inform the company official about the results of the assessment,
Prepares the Audit Report according to “F - 139 TS EN ISO 3834 Audit Report ve.
It is also signed by the company representative. Nonconformities detected during the audit,
observations and planned corrective action dates are recorded in the audit reports.
Non-conformities that would prevent certification for the continuation of the certification process
is expected to be resolved.
- i) Closing meeting, at least one person from the company management and related to the process to be certified
with the participation of the authorities. Evaluation results, nonconformities, if any,
deficiencies, suggestions and / or follow-up audit information if necessary
Transmitted. The participants of the meeting stated that the “F - 174 Opening-Closing Meeting Minutes ilgili
section.
- k) Certification of the Audit Report submitted by the Lead Auditor and Auditors
Following the evaluation by the Board, the company fulfills the requirements of TS EN ISO 3834.
the customer is considered “in conformity eye with the relevant certification.
Signing of the Audit Report by the Certification Board has decided to certify
It is proof. This decision was made by the Process-Product Certification Manager / Directive Manager.
the customer is notified in writing. The Quality Engineer prepares the certificate in accordance with the standard.
The publication date of the certificate is the date on which the certification body approves the file.
Regulated. Explanation of the validity period or validity period of the certificates
overwritten. TS EN ISO 3834-2 / -3 standards after the studies
If there is no change in the certificates issued, only sadece F - 181 TS
EN ISO 3834 Surveillance Audit Checklist
oversight is made. However, changes such as scope, company address, resource coordinator etc.
certification in case of mutual negotiations with the company.
Inspection date is determined by the engineer. TS EN ISO 3834, documents 3 year
validity period. This period of validity of the surveillance audits defined in the standard
valid if done successfully.
- l) The certificate is signed by GSI SLV-TR Company Manager.
site is added to the certified company list.